Mixing

Mixing shall be carried out by mechanical means e.g. a mortar mixer. OPC and sand are first poured into the mixer followed by clean water and AD 017. The whole content is mixed for minimum 3 minutes until a homogeneous mortar consistency is obtained. Avoid prolonged mixing once the desired consistency is achieved. Depending on the ambient condition, the mixture should be consumed within one hour for best workability. For mortar which has set, do not re-temper by mixing in additional water as this will adversely affect the final properties.

Placing The Screed

Place the fresh mortar using a wooden or aluminum straightedge following standard construction practice

Curing

The freshly laid screed should be cured for at least 7 days prior to receiving tiles or other coverings.